Accordingly, the repair of branch S1H of AAGwill finish on January 9, one week later than initially planned, and of branchS1I January 15.
Meanwhile, the problem on the Asia Africa Europe(AAE-1) cable will be fixed from January 22 to January 27.
Repair work on branches S2 and S1 of TataTGN-Intra Asia (IA) cable is scheduled to be completed on January 29 andFebruary 3.
On December 22, the three cables concurrentlyencountered problems, causing a loss of 30 percent to the internationalinternet transmission capacity of Vietnam.
With the above-mentioned schedule, the country’sinternational internet transmission capacity will be fully recovered beforeTet. However, the repair plan could also be changed depending on weatherconditions at sea./.