The 139-km transmissionline, which runs through three northern provinces of Quang Ninh, HaiDuong and Bac Giang, was built with a total investment of over 2.2trillion VND (approximately 107 million USD) funded by World Bank loansand domestic counterpart capital.
The line willensure the transmission of electricity from the Quang Ninh-Mong Duongthermal power complex to the national grid, meeting the rising demandfor power in the northern region as well as in the country as a whole.
According to the EVN NPT, the powertransmission system will be able to meet the economy’s demand for anannual amount of 145-150 billion kWh in 2015, and 265-275 billion kWh by2020.
The corporation will maintainand extend the 220-500 kV transmission system connected with China,Laos and Cambodia, looking to building a smart grid capable of improvingthe quality of electricity supply service.-VNA