The changes were announced atJuly 16 conferences in Thuan Nam and Ninh Hai districts of the centralprovince of Ninh Thuan, where the two respective power plants are based.
Ninh Thuan 1 power plant in Vinh Truong village,Thuan Nam district will sprawl over 443.11 hectares of land and 440.57hectares at sea.
Ninh Thuan 2 power plant, based inThai An village, Ninh Hai district, will spread 380.91 hectares of landand 337.63 hectares at sea.
Each will be equipped with four 1,000-1,200 megawatt turbines installed over two phases.
Local authorities are responsible for resident resettlement to pavethe way for the construction, which has been delayed a number of timesfollowing safety lessons learned from the 2011 Fukushima nuclearincident in Japan, with an initial focus on infrastructure, such asroads and water and electricity supply.
In collaboration with the Electricity of Vietnam, they will build synchronous infrastructure within and near the plants.
The first turbine of Ninh Thuan 1 plant is expected to be connected to the national grid by 2020.-VNA