Dung madethe request while inspecting three key infrastructure projects of Hanoiincluding the Mai Dich-Thang Long Bridge section on the city’s Belt Road No 3and urban railway lines No 2A Cat Linh-Ha Dong and No 3 Nhon-Hanoi TrainStation.
TheMinistry of Transport and the railway’s general contractor must hasten work inorder to start operating the project as soon as possible in 2019, he said.
However,the Deputy PM also stressed that the top priority is to secure safety duringoperation and the safety certificate must be approved before running the train.
Constructionon the over 20 trillion VND (886 million USD) Cat Linh-Ha Dong urban railwaystarted in 2011 and was initially expected to be completed in 2015. Theconstruction deadline was later set at 2018 with trial runs to be ended byMarch 31 this year.
Sixmonths after the trial period, however, an exact date on when Hanoians canfinally board the train remains up in the air./.